Phase 2 of 9
Your responsibilities for the steel phase — from sub coordination through final walk-through.
The steel cage is the skeleton of your pool. Everything that comes later — plumbing, gunite, plaster — depends on it being placed exactly to plan. Walk the cage carefully, ask questions, and don't sign off until every feature is built in.
Customize first. Some items only apply to certain projects (spa, fountains, art rock, etc.). Toggle the Project Options below before printing or sharing.
Cage is complete, features are built in, bonding is in place. You're set up for plumbing.